Kesem Dam and Irrigation Development Project
Completed
Kesem Dam and Irrigation Development Project
Region
Afar National Regional State
Zone | Woreda
Three | Kesem and Golehamo
Equipped Areas
4,000 Hectares
Type of Headwork
Zoned rock fill Dam with central impervious core
Date Started
March, 1997 Ethiopian Calendar
Date Completed
June, 2007 Ethiopian Calendar
Project Cost
2.75 Billion Ethiopian Birr
Irrigation System
Furrow

Lower Genale Feasibility Study and Detail Design of Irrigation Project (Lot-II)
On Going
Lower Genale Feasibility Study and Detail Design of Irrigation Project (Lot-II)
Region
Somali National Regional State
Zone | Woreda
Liben and Afder | Dolo-ado, Bekolmayu and Dolo-bay
Equipped Areas
38,000 Hectares
Type of Headwork
Diversion Storage and Lifting
Date Contracted
June, 2021 GCE
Date Completed - Expected
November, 2022 GCE
Project Cost
96,082,127.93 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Ribb Dam Construction Project
On Going
Lower Genale Feasibility Study and Detail Design of Irrigation Project (Lot-II)
Region
Somali National Regional State
Zone | Woreda
Liben and Afder | Dolo-ado, Bekolmayu and Dolo-bay
Equipped Areas
38,000 Hectares
Type of Headwork
Diversion Storage and Lifting
Date Contracted
June, 2021 GCE
Date Completed - Expected
November, 2022 GCE
Project Cost
96,082,127.93 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Megech Serba (Pump) Irrigation Development Project
Completed
Megech Serba (Pump) Irrigation Development Project
Region
Amhara National Regional State
Zone | Woreda
Central Gonder | West Dambia and East Dambia
Equipped Areas
4040 Hectares
Type of Headwork
Pumping Station
Date Started
October, 2005 Ethiopian Calendar
Date Completed
September, 2012 Ethiopian Calendar
Project Cost
1.6 Billion Ethiopian Birr
Irrigation System
Furrow

Gillo Feasibility Study and Detail Design of Irrigation Project
On Going
Gillo Feasibility Study and Detail Design of Irrigation Project
Region
Gambella National Regional State
Zone | Woreda
Agnuwak | Gog
Equipped Areas
20,000 Hectares
Type of Headwork
Storage Dam
Date Contracted
June, 2020 GCE
Date Completed - Expected
30 October 2021 GCE (due to a conflict the project has been delayed for 16 months so it
needs contract amendment)
Project Cost
37,930,611.05 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Shinfa Feasibility Study and Detail Design of Irrigation Project
On Going
Shinfa Feasibility Study and Detail Design of Irrigation Project
Region
Amhara National Regional State
Zone | Woreda
North Western part of Abay Basin near Tewodros Ketema town | Metema
Equipped Areas
86,500 Hectares
Type of Headwork
Storage Dam
Date Contracted
December, 2022 GCE
Date Completed - Expected
December 2022 GCE (due to security problems the contract is under suspension)
Project Cost
127,241,861.78 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Koga Dam and Irrigation Development Project
Completed
Koga Dam and Irrigation Development Project
Region
Amhara National Regional State
Zone | Woreda
West Gojam | Mecha woreda
Equipped Areas
7200 Hectares
Type of Headwork
Rock fill Dam with central impervious core
Date Started
November, 1997 Ethiopian Calendar
Date Completed
May, 2003 Ethiopian Calendar
Project Cost
1.142 Billion Ethiopian Birr
Irrigation System
Furrow

Lower (Abat) Beles Feasibility Study and Detail Design of Irrigation Project
On Going
Lower (Abat) Beles Feasibility Study and Detail Design of Irrigation Project
Region
Benishangul- Gumuz National Regional State
Zone | Woreda
Metekel | Mandura, Pawi and Dangureand
Equipped Areas
6,000 Hectares
Type of Headwork
Storage Dam
Date Contracted
May, 2020 GCE
Date Completed - Expected
March 2021 GCE(due to security problems the contract is under suspension)
Project Cost
14,039,538.65 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Gidabo Dam Construction Project
Completed
Gidabo Dam Construction Project
Region
Oromiya and Sidama National Regional States
Zone | Woreda
West Guji and Sidama | Abaya and Loko Abaya
Equipped Areas
___
Type of Headwork
Zoned rock fill Dam with Central impervious core
Date Started
January, 2002 Ethiopian Calendar
Date Completed
June, 2011 Ethiopian Calendar
Project Cost
1.6 Billion Ethiopian Birr
Irrigation System
Traditional Furrow

The Chelchel Irrigation Development Project is underway with a 5.5 Billion Ethiopian Birr budget.
Mesfin
Under the ownership of the Ministry of Irrigation and Lowlands (MILLs), the construction of the 5.5 Billion Ethiopian Birr Irrigation Development project is underway in the Raitu and Ginir Woredas of Eastern Bale Zone in the Oromia Region. Upon completion, the project will cover an area of 4,146 hectares and will significantly benefit more than 9,000 pastoralists and semi-pastoralists.
Located at the border of Raitu and Ginir, the Chelchel river (a tributary of the Weyib River) is the site of the Chelchel Dam Construction Project. The Irrigation Development System will be located in Raitu Woreda. The Chelchel Dam will span across 46.5meters high and 681 meters long with a staggering capacity of 50 million cubic meters of water, covering an area of 341.8 hectares. Furthermore, the water will recede up to a distance of 1.5km.
Upon its completion, Raitu Woreda will be able to harvest crops such as maize, wheat, millet, papaya, banana, onions, and tomatoes twice or three times a year.
The construction of The Dam and Irrigation Development will primarily involve the construction of a 47.5km main canal, which will be followed by the construction of the left and right sections spanning 21.5km and 22.6km respectively. Moreover, a 35.3km second canal and a third canal covering a distance of 168km will be built.
This project has been divided into two lots: Although the first contractor who was in charge of Lot I terminated their contract, in their place, Alemayehu Ketema General Contractor entered into a contract. They have since taken over and are currently mobilizing the necessary resources, machinery, and manpower to resume the work. As for Lot II, Oromia Construction Corporation (whose contract was renewed twice) is in charge and could face difficulties completing the project on schedule if it doesn’t deploy the required machinery promptly.
By the end of March in the current Ethiopian fiscal year, the construction of the project has reached 13.8% in Lot I and 74.75% in Lot II.
A total of 509 citizens, comprising 430 men and 79 women, were employed on a temporary and permanent basis as part of the project. The project has faced several challenges including capacity of sub-contractors, shortage of labor & shortage of machinery. As a result, discussions were held with the concerned stakeholders to devise solutions in order to address these challenges.
The project commenced in December 2012 (E.C.) and is scheduled for completion by the end of the 2018 Ethiopian Fiscal Year.